Wetlands
$535,649
About 1.8 acres of grading and planting at Grandy Village along the Eastern Branch of the Elizabeth River.
Status 100 percent complete, about $534,843 invoiced through Nov. 2008.
Viaduct
$13.6 million
Viaduct construction between Harbor Park and Norfolk State University. Includes a 3,400-foot elevated structure and relocating Holt Street.
Status 67.6 percent complete, about $9.2 million invoiced through Nov. 2008.
East end track
$40.9 million
Norfolk Southern right of way between Norfolk State and Newtown Road. Includes bridges over Broad Creek and Norfolk Southern tracks.
Status 23 percent complete, about $9.4 million invoiced through Nov. 2008.
West end track
$42.4 million
Construction of a light-rail bridge parallel to Brambleton Avenue over Smith Creek is shown. The contract includes laying track from Harbor Park through downtown to the medical complex.
Status 6.6 percent complete, about $2.8 million invoiced through Nov. 2008.
WHAT'S NEXT?
Electrical work
The work will include poles, wires, substations and grade crossings and gates.
Cost $27.7 million
Storage site
Light-rail vehicle storage and maintenance facility.
Cost $11 million