Light rail's new promised price tag: $338.3 million

Posted to: Light Rail News Norfolk

HAMPTON

Hampton Roads Transit vowed Thursday to complete construction of Norfolk's beleaguered light-rail project for $338.3 million, slightly less than anticipated but still 46 percent more than original estimates.

Most of the increase is for expenses related to schedule delays that have caused bills for expanded overhead costs and idle equipment to pile up, according to a report by consultant AECOM.

The delays were caused mainly by challenges with utility relocations downtown and by last-minute changes and additions to the project.

For months it's been clear that light rail was running way over budget, but the numbers had not been pinpointed. Estimates ranged from $325 million to, most recently, $340 million. When construction began in the fall of 2007, the price tag was $232.1 million. That number rose to $288 million about a year ago.

On his first day on the job, Feb. 1, HRT's new leader, Philip Shucet, started working with staff to develop a final "cost-to-complete" that the agency could "own." They were aided by work already conducted by HRT and AECOM, hired by former President and CEO Michael Townes, who was forced to step down last month as costs and communication problems grew.

Asked by HRT board members how confident he is in the new figure, Shucet responded, "We're not going to add a penny to that."

He added that passengers will board in May 2011.

"I'm gratified we have, at last, a number that we can have a high degree of confidence in," said Jim Wood, HRT chairman and Virginia Beach councilman.

Vice chairman W. Randy Wright, a Norfolk councilman, said, "For the first time, we know where we are, when we're going to finish and how we're going to finish."

Shucet could not answer on Thursday how he planned to cover the extra costs beyond the previous $288 million budget. Already, the state has contributed an extra $20 million, leaving a $30 million gap.

He said he's looking at other federal, state and even HRT sources for funding. Federal authorities may kick in additional money for safety upgrades.

If no other money is found, Norfolk is ultimately responsible, but Shucet said he's trying to avoid asking the city for more.

HRT's financial review shows that "soft costs," such as design work, consultant fees and real estate, are coming in at more than double the original estimates and that they account for 45 percent of the new project price tag.

Going forward, Shucet has eliminated a layer of consultants that were managing the project, saving $7 million and reducing the soft costs to 10 percent of the project budget for the remainder of the construction period.

Hard costs, or actual building costs, have risen 37 percent since construction began.

Shucet told the board that HRT missed an early warning that something was amiss when the bid for constructing the downtown segment of track came in nearly 75 percent higher than budgeted.

"That was the time to take a deliberate look at the entire budget," Shucet said in a letter to the board Thursday. "The message in that bid is palpable: There is more risk here than you know.... Projects that start right usually end right. We faltered early."

HRT board member Rick West, a Chesapeake councilman, said he feels some guilt for not asking the right questions or pushing management hard enough.

"There's a valuable lesson in here for us: dig, dig, dig, ask, ask, ask," West said.

AECOM's report, dated Jan. 27, reveals that schedule delays are to blame for most of the cost increases. The report offers some specific examples:

The electrical contractor has been delayed 280 days - at an estimated cost of $3.3 million - because of additional work and because track installation was slowed.

Another contract is behind 360 days, at a cost of $1.6 million, waiting for changes requested by Norfolk State University in the design of the maintenance and storage facility. That delay has created another unexpected expense - building a temporary shelter for light-rail vehicles.

And because the opening date has been pushed back from October 2010 until mid-2011, expenses are building for the idle light-rail vehicles on the track next to NSU. A warranty extension for the cars is estimated to cost about $138,000.

HRT's written summary of its financial review states that because construction is 62 percent complete, the unexpected costs are "becoming increasingly smaller as the project rises out of the ground."

Even with the latest overruns, the project remains the cheapest among recent rail projects in the country, at around $45.7 million per mile. The next cheapest is Charlotte, N.C., at $48 million per mile.

Debbie Messina, (757) 446-2588, debbie.messina@pilotonline.com

COMMENTS ADVISORY: Users are solely responsible for opinions they post here; comments do not reflect the views of The Virginian-Pilot or its websites. Users must follow agreed-upon rules: Be civil, be clean, be on topic; don't attack private individuals, other users or classes of people. Read the full rules here.
- Comments are automatically checked for inappropriate language, but readers might find some comments offensive or inaccurate. If you believe a comment violates our rules, click the report violation link below it.

I support LRail but disagree with motives of those who oppose

Submitted by Mr. Wizard on Fri, 02/19/2010 at 4:20 pm. "Costs overun isnt the real issue..if we want to overcome racism in this State, we need to do expand light rail."

Mr. Wizard, while I agree with you in the above statement, I don't think it's fair to say that everyone who opposes light rail is a racist.

We are enjoying a savings of $2.3 Million per mile

"the project remains the cheapest among recent rail projects in the country, at around $45.7 million per mile. The next cheapest is Charlotte, N.C., at $48 million per mile."

When you calculate up the savings per mile along with the enviromental benefit the project pays for itself and actually we make money.

"the project pays for itself"

By golly, those calculations should be publicized far and wide to show that no more taxpayer money will be needed.

Please show the calculations, susanj.

Thank You giving us another lesson susanj52739

Susanj52739, if you study her postings is, well, a professional.

Welcome to the professional blogosphere, where money matters.

shimmer your concerns

shimmer said "The schools in Norfolk are old, flooding continues to plague certain neighborhoods, gangs are infiltrating our neighborhoods, pot holes all over, no raises for police, fire fighters and city employees, etc"

The savings from Light Rail will take care of all of those issues and more.

Savings from Light Rail can fund our schools and rebuild highway

Potential Operating Savings from Light Rail
Light Rail LR PM LR $/PM Bus $/PM Savings

Portland 169,572 0.33 0.72 67,163
St. Louis 124,973 0.29 0.88 72,798

great way to use garbage to support your view

I am a native St. Louisan, and I ask: why don't you mention the fact that the city is saying they need $68million to get the Metro operating back in the black. They recently reduced train coverage and schedules to save some cash. The entire Metro system is in danger of shutting down...and it actually serves the greater city / county area with service to the stadium, the two markets, international airport, etc....and where is the Tide going to go? Newtown Rd. There is NO WAY the it will EVER pay for itself...not in this tiny-minded region of little feifdoms....

I'm jus' sayin'...

Norfolk is not Portland or St. Louis

Portland has 582,000 people
Average Ridership - 112,000-115,000 per day (2009)

St, Louis has 991,000 people
Average Ridership - 58,000 per day (2009)

Norfolk has 239,000 people
Average Ridership estimated at 8,000-12,000 per day

If it connected the basis or major hubs like Greenbriar and the VA Beach Town Center then I could see your arguement.

Light Rail could save us over a Hundred Million $

http://www.ti.org/vaupdate57.html

even if the light rail costs double. We will still come out way ahead.

Link from Susan has a virus

Just kidding, however the web page you send people to is dated 2005. We are living in different economic times and would like to see updated numbers.

The question isn't really if light rail is good or not, it is whether Norfolk should have invested in a project this large before addressing areas of need.

The schools in Norfolk are old, flooding continues to plague certain neighborhoods, gangs are infiltrating our neighborhoods, pot holes all over, no raises for police, fire fighters and city employees, etc. Norfolk's share of this project could have been better used for projects we really need.

Comment viewing options

Select your preferred way to display the comments and click "Save settings" to activate your changes.
Please note: Threaded comments work best if you view the oldest comments first.

More articles from: News rss feed   



Toolbox


special features